Energy projects / Germany / Niedersachsen
Battery and other storage projects in Niedersachsen, Germany
130 battery and other storage projects of 1 MW and up in Niedersachsen, Germany: 76 in the pipeline (523 MW planned, consented or under construction) and 48 in operation (688 MW). Source: Arcadium Data, data as of .
Use it through the API License the full dataset
Projects by stage
| Stage | Projects | Capacity |
|---|---|---|
| Planned (scoping or in planning) | 76 | 523 MW |
| In operation | 48 | 688 MW |
| Temporarily shut down | 6 | 8 MW |
Largest projects in the pipeline
| Project | Technology | Stage | Capacity | Expected | Where | Operating company |
|---|---|---|---|---|---|---|
| Battery and other storage project | Battery and other storage | Planned (scoping or in planning) | 147 MW | 2027-05-20 | Hilgermissen, Niedersachsen | Kyon-56 Battery Storage GmbH |
| Battery and other storage project | Battery and other storage | Planned (scoping or in planning) | 45 MW | 2026-12-21 | Lehrte, Niedersachsen | enercity BESS Lehrte-Ahlten 1 GmbH & Co. KG |
| Battery and other storage project | Battery and other storage | Planned (scoping or in planning) | 22 MW | 2026-12-23 | Hannover, Niedersachsen | enercity BESS Hannover-Misburg GmbH & Co. KG |
| Battery and other storage project | Battery and other storage | Planned (scoping or in planning) | 20 MW | 2026-10-01 | Salzgitter, Niedersachsen | Volkswagen Group Charging |
| Battery and other storage project | Battery and other storage | Planned (scoping or in planning) | 15 MW | 2026-12-01 | Visbek, Niedersachsen | Terra One Energy Grid 3 GmbH |
| Battery and other storage project | Battery and other storage | Planned (scoping or in planning) | 15 MW | 2025-12-04 | Ahlerstedt, Niedersachsen | Terra One Energy Grid 2 GmbH |
| Battery and other storage project | Battery and other storage | Planned (scoping or in planning) | 13 MW | 2026-11-30 | Brietlingen, Niedersachsen | |
| Battery and other storage project | Battery and other storage | Planned (scoping or in planning) | 12 MW | 2027-02-01 | Schöningen, Niedersachsen | SMAREG 15 GmbH & Co. KG |
| Battery and other storage project | Battery and other storage | Planned (scoping or in planning) | 8 MW | 2026-12-23 | Ronnenberg, Niedersachsen | enercity BESS Ronnenberg- Empelde GmbH & Co. KG |
| Battery and other storage project | Battery and other storage | Planned (scoping or in planning) | 8 MW | 2028-02-01 | Bokensdorf, Niedersachsen | SolarPark BOKENSDORF GmbH |
| Battery and other storage project | Battery and other storage | Planned (scoping or in planning) | 7 MW | 2026-05-01 | Brinkum, Niedersachsen | ENERPARC Solar Invest 230 TU 7 GmbH & Co. KG |
| Battery and other storage project | Battery and other storage | Planned (scoping or in planning) | 7 MW | 2027-05-31 | Ahausen, Niedersachsen | ENERPARC Solar Invest 230 TU 36 GmbH & Co. KG |
| Battery and other storage project | Battery and other storage | Planned (scoping or in planning) | 7 MW | 2028-04-15 | Ehra-Lessien, Niedersachsen | AS Energy 14 GmbH & Co. KG |
| Battery and other storage project | Battery and other storage | Planned (scoping or in planning) | 6 MW | 2027-04-01 | Bad Bentheim, Niedersachsen | Fünfundzwanzigste Bürgerwindpark GmbH & Co. KG |
| Battery and other storage project | Battery and other storage | Planned (scoping or in planning) | 6 MW | 2027-10-01 | Bissendorf, Niedersachsen | EFG Energy-Farming Holding GmbH |
| Battery and other storage project | Battery and other storage | Planned (scoping or in planning) | 6 MW | 2027-10-01 | Bohmte, Niedersachsen | Energiepark Bohmte Wind GmbH & Co. KG |
| Battery and other storage project | Battery and other storage | Planned (scoping or in planning) | 6 MW | 2026-06-05 | Badbergen, Niedersachsen | trlyr 10 GmbH & Co. KG |
| Battery and other storage project | Battery and other storage | Planned (scoping or in planning) | 6 MW | 2027-08-01 | Oldendorf (Luhe), Niedersachsen | Solarpark Dehnsen - Wohlenbüttel GmbH & Co. KG |
| Battery and other storage project | Battery and other storage | Planned (scoping or in planning) | 6 MW | 2027-04-30 | Salzbergen, Niedersachsen | VENDO SOLAR Park Salzbergen ll GmbH & Co. KG |
| Battery and other storage project | Battery and other storage | Planned (scoping or in planning) | 5 MW | 2027-04-15 | Egestorf, Niedersachsen | Solarpark Waldsiedlung Egestorf GmbH Co. KG |
| Battery and other storage project | Battery and other storage | Planned (scoping or in planning) | 5 MW | 2026-12-01 | Walsrode, Niedersachsen | Solarpark Schneeheide GmbH & Co. KG |
| Battery and other storage project | Battery and other storage | Planned (scoping or in planning) | 5 MW | 2026-12-01 | Walsrode, Niedersachsen | Solarpark Elbenhorst GmbH & Co. KG |
| Battery and other storage project | Battery and other storage | Planned (scoping or in planning) | 5 MW | 2028-01-01 | Hassel (Weser), Niedersachsen | M+S Wind GmbH & Co KG |
| Battery and other storage project | Battery and other storage | Planned (scoping or in planning) | 5 MW | 2026-12-01 | Walsrode, Niedersachsen | Solarpark Eichberg-Lindenberg GmbH & Co. KG |
| Battery and other storage project | Battery and other storage | Planned (scoping or in planning) | 5 MW | 2026-12-01 | Walsrode, Niedersachsen | 27. Lintas Energiepark GmbH & Co. KG |
Operating companies
| Operating company | Projects | Capacity |
|---|---|---|
| Statkraft Markets GmbH | 2 | 205 MW |
| Kyon-56 Battery Storage GmbH | 1 | 147 MW |
| Scale Alfeld GmbH & Co. KG | 1 | 138 MW |
| RWE Supply & Trading GmbH | 1 | 45 MW |
| enercity BESS Lehrte-Ahlten 1 GmbH & Co. KG | 1 | 45 MW |
| RheinEnergie Speicher Einbeck GmbH & Co. KG | 1 | 25 MW |
| enercity BESS Hannover-Misburg GmbH & Co. KG | 1 | 22 MW |
| Energiepark Bohmte Wind GmbH & Co. KG | 5 | 22 MW |
| trlyr 8 GmbH & Co. KG | 1 | 20 MW |
| Volkswagen Group Charging | 1 | 20 MW |
| trlyr 9 GmbH & Co. KG | 1 | 17 MW |
| SWO Energie Leer Nord GmbH | 1 | 15 MW |
| Avacon Natur GmbH | 1 | 15 MW |
| Terra One Energy Grid 2 GmbH | 1 | 15 MW |
| Terra One Energy Grid 3 GmbH | 1 | 15 MW |
| trlyr 5 GmbH & Co. KG | 1 | 15 MW |
| enercity AG | 1 | 14 MW |
| trlyr 31 GmbH & Co. KG | 1 | 13 MW |
| SMAREG 15 GmbH & Co. KG | 1 | 12 MW |
| be.storaged GmbH | 1 | 12 MW |
| NewDev Solarpark Tiste ApS & Co. KG | 3 | 11 MW |
| PEE3 GmbH & Co. KG | 3 | 10 MW |
| PASM GmbH | 2 | 9 MW |
| enercity BESS Ronnenberg- Empelde GmbH & Co. KG | 1 | 8 MW |
| ISP Salzbergen GmbH & Co. KG | 6 | 8 MW |
Projects of 1 MW and up. Capacity is net nominal capacity (Germany) or the total capacity of the queue entry (Great Britain). A hybrid project counts under each technology it lists. Companies only: private persons are never shown as operators, and no coordinates or street addresses are published. Data as of 2026-10-25, updated monthly.
Germany: Marktstammdatenregister, Bundesnetzagentur, Datenlizenz Deutschland - Namensnennung - Version 2.0 (www.govdata.de/dl-de/by-2-0). Great Britain: Supported by National Energy SO Open Data (NESO Open Data Licence, TEC register and Embedded register).
Questions
Where does this data come from?
Germany: the public Marktstammdatenregister of the Bundesnetzagentur, including units in planning. We load the official files, keep projects of 1 MW and up and record changes between loads.
Does the list show private owners?
No. Operators are shown only when they are companies. Private persons, sole traders and names that could belong to a person are left out, and the data holds no coordinates or street addresses.
How often is it updated?
Monthly. Each load records new projects, changes of stage, capacity or connection date, and projects that left the register.
Cite as: Arcadium Data, "Battery and other storage projects in Niedersachsen, Germany: 76 in the pipeline, 523 MW", https://arcadiumdata.io/energy/de/niedersachsen/storage/, data as of 2026-10-25.