Energy projects / Germany / Baden-Wuerttemberg
Battery and other storage projects in Baden-Wuerttemberg, Germany
127 battery and other storage projects of 1 MW and up in Baden-Wuerttemberg, Germany: 55 in the pipeline (620 MW planned, consented or under construction) and 70 in operation (2,050 MW). Source: Arcadium Data, data as of .
Use it through the API License the full dataset
Projects by stage
| Stage | Projects | Capacity |
|---|---|---|
| Planned (scoping or in planning) | 55 | 620 MW |
| In operation | 70 | 2,050 MW |
| Temporarily shut down | 1 | 1 MW |
| Decommissioned | 1 | 22 MW |
Largest projects in the pipeline
| Project | Technology | Stage | Capacity | Expected | Where | Operating company |
|---|---|---|---|---|---|---|
| Battery and other storage project | Battery and other storage | Planned (scoping or in planning) | 300 MW | 2029-10-01 | Deißlingen, Baden-Wuerttemberg | ECO POWER SIX GmbH |
| Battery and other storage project | Battery and other storage | Planned (scoping or in planning) | 100 MW | 2026-12-31 | Marbach am Neckar, Baden-Wuerttemberg | EnBW Energie Baden-Württemberg AG |
| Battery and other storage project | Battery and other storage | Planned (scoping or in planning) | 18 MW | 2027-02-01 | Baindt, Baden-Wuerttemberg | SMAREG 10 GmbH & Co. KG |
| Battery and other storage project | Battery and other storage | Planned (scoping or in planning) | 12 MW | 2026-09-30 | Crailsheim, Baden-Wuerttemberg | ingenia GES Onolzheim GmbH |
| Battery and other storage project | Battery and other storage | Planned (scoping or in planning) | 12 MW | 2026-09-07 | Karlsruhe, Baden-Wuerttemberg | Firma Stadtwerke Karlsruhe GmbH |
| Battery and other storage project | Battery and other storage | Planned (scoping or in planning) | 12 MW | 2026-11-02 | Wehr, Baden-Wuerttemberg | 8Energies Wehr GmbH |
| Battery and other storage project | Battery and other storage | Planned (scoping or in planning) | 10 MW | 2027-06-01 | Tauberbischofsheim, Baden-Wuerttemberg | juwi Wind Germany 296 GmbH & Co. KG |
| Battery and other storage project | Battery and other storage | Planned (scoping or in planning) | 10 MW | 2026-12-03 | Willstätt, Baden-Wuerttemberg | NEOEN Speicher 6 |
| Battery and other storage project | Battery and other storage | Planned (scoping or in planning) | 10 MW | 2027-06-01 | Stuttgart, Baden-Wuerttemberg | Becken Energiespeicher 1 GmbH & Co. KG |
| Battery and other storage project | Battery and other storage | Planned (scoping or in planning) | 10 MW | 2025-06-30 | Stuttgart, Baden-Wuerttemberg | EnBW Energie Baden-Württemberg AG |
| Battery and other storage project | Battery and other storage | Planned (scoping or in planning) | 7 MW | 2027-01-01 | Schöntal, Baden-Wuerttemberg | Bürger-PV Berlichingen GmbH & Co. KG |
| Battery and other storage project | Battery and other storage | Planned (scoping or in planning) | 6 MW | 2027-09-01 | Schömberg, Baden-Wuerttemberg | ABO Energy Solarpark 6 GmbH & Co. KG |
| Battery and other storage project | Battery and other storage | Planned (scoping or in planning) | 5 MW | 2026-11-01 | Waldkirch, Baden-Wuerttemberg | Reservestrom Waldkirch GmbH |
| Battery and other storage project | Battery and other storage | Planned (scoping or in planning) | 5 MW | 2027-12-01 | Empfingen, Baden-Wuerttemberg | wpd Solarpark A81 GmbH & Co. KG |
| Battery and other storage project | Battery and other storage | Planned (scoping or in planning) | 5 MW | 2026-06-30 | Blaubeuren, Baden-Wuerttemberg | Windenergie Kraiß Gesellschaft mbH |
| Battery and other storage project | Battery and other storage | Planned (scoping or in planning) | 5 MW | 2026-12-14 | Bruchsal, Baden-Wuerttemberg | BESS Bruchsal GmbH & Co. KG |
| Battery and other storage project | Battery and other storage | Planned (scoping or in planning) | 5 MW | 2026-04-17 | Sigmaringen, Baden-Wuerttemberg | EnBW Solar GmbH |
| Battery and other storage project | Battery and other storage | Planned (scoping or in planning) | 4 MW | 2028-02-01 | Achstetten, Baden-Wuerttemberg | Solarpark Achstetten GmbH & Co. KG |
| Battery and other storage project | Battery and other storage | Planned (scoping or in planning) | 4 MW | 2027-09-01 | Friedrichshafen, Baden-Wuerttemberg | Rolls-Royce Solutions |
| Battery and other storage project | Battery and other storage | Planned (scoping or in planning) | 4 MW | 2027-09-01 | Friedrichshafen, Baden-Wuerttemberg | Rolls-Royce Solutions |
| Battery and other storage project | Battery and other storage | Planned (scoping or in planning) | 4 MW | 2026-10-01 | Mögglingen, Baden-Wuerttemberg | Anumar Solarpark Mögglingen GmbH & Co. KG |
| Battery and other storage project | Battery and other storage | Planned (scoping or in planning) | 4 MW | 2027-01-18 | Biberach an der Riß, Baden-Wuerttemberg | |
| Battery and other storage project | Battery and other storage | Planned (scoping or in planning) | 4 MW | 2027-12-01 | Horb am Neckar, Baden-Wuerttemberg | wpd Solarpark A81 GmbH & Co. KG |
| Battery and other storage project | Battery and other storage | Planned (scoping or in planning) | 3 MW | 2026-12-01 | Riedlingen, Baden-Wuerttemberg | BS I GmbH |
| Battery and other storage project | Battery and other storage | Planned (scoping or in planning) | 3 MW | 2026-12-01 | Zimmern ob Rottweil, Baden-Wuerttemberg | Elektrizitätswerke Schönau Energie GmbH |
Operating companies
| Operating company | Projects | Capacity |
|---|---|---|
| Schluchseewerk AG | 20 | 1,786 MW |
| ECO POWER SIX GmbH | 1 | 300 MW |
| EnBW Energie Baden-Württemberg AG | 8 | 227 MW |
| EnBW Solar GmbH | 8 | 32 MW |
| SMAREG 10 GmbH & Co. KG | 1 | 18 MW |
| Tauber-Solar Management GmbH | 1 | 16 MW |
| Firma Stadtwerke Karlsruhe GmbH | 1 | 12 MW |
| ingenia GES Onolzheim GmbH | 1 | 12 MW |
| 8Energies Wehr GmbH | 1 | 12 MW |
| Solarpark 107 GmbH & Co. KG | 3 | 11 MW |
| Becken Energiespeicher 1 GmbH & Co. KG | 1 | 10 MW |
| juwi Wind Germany 296 GmbH & Co. KG | 1 | 10 MW |
| Kessler & Co. | 2 | 10 MW |
| NEOEN Speicher 6 | 1 | 10 MW |
| 5.DGS Energie Projekt GmbH & Co. KG | 1 | 9 MW |
| Brandstätter Solarpark GmbH & Co. KG | 1 | 8 MW |
| Aranea Battery Solutions | 2 | 8 MW |
| Rolls-Royce Solutions | 2 | 8 MW |
| SchwörerHaus KG | 2 | 8 MW |
| Bürger-PV Berlichingen GmbH & Co. KG | 1 | 7 MW |
| ABO Energy Solarpark 6 GmbH & Co. KG | 1 | 6 MW |
| LHI SolarWind PV Gammertingen 2695 GmbH & Co. KG | 1 | 5 MW |
| Reservestrom Waldkirch GmbH | 1 | 5 MW |
| Windenergie Kraiß Gesellschaft mbH | 1 | 5 MW |
| BESS Bruchsal GmbH & Co. KG | 1 | 5 MW |
Projects of 1 MW and up. Capacity is net nominal capacity (Germany) or the total capacity of the queue entry (Great Britain). A hybrid project counts under each technology it lists. Companies only: private persons are never shown as operators, and no coordinates or street addresses are published. Data as of 2026-10-25, updated monthly.
Germany: Marktstammdatenregister, Bundesnetzagentur, Datenlizenz Deutschland - Namensnennung - Version 2.0 (www.govdata.de/dl-de/by-2-0). Great Britain: Supported by National Energy SO Open Data (NESO Open Data Licence, TEC register and Embedded register).
Questions
Where does this data come from?
Germany: the public Marktstammdatenregister of the Bundesnetzagentur, including units in planning. We load the official files, keep projects of 1 MW and up and record changes between loads.
Does the list show private owners?
No. Operators are shown only when they are companies. Private persons, sole traders and names that could belong to a person are left out, and the data holds no coordinates or street addresses.
How often is it updated?
Monthly. Each load records new projects, changes of stage, capacity or connection date, and projects that left the register.
Cite as: Arcadium Data, "Battery and other storage projects in Baden-Wuerttemberg, Germany: 55 in the pipeline, 620 MW", https://arcadiumdata.io/energy/de/baden-wuerttemberg/storage/, data as of 2026-10-25.