Energy projects / Germany / Nordrhein-Westfalen
Biomass projects in Nordrhein-Westfalen, Germany
197 biomass projects of 1 MW and up in Nordrhein-Westfalen, Germany: 37 in the pipeline (73 MW planned, consented or under construction) and 137 in operation (499 MW). Source: Arcadium Data, data as of .
Use it through the API License the full dataset
Projects by stage
| Stage | Projects | Capacity |
|---|---|---|
| Planned (scoping or in planning) | 37 | 73 MW |
| In operation | 137 | 499 MW |
| Temporarily shut down | 4 | 5 MW |
| Decommissioned | 19 | 78 MW |
Largest projects in the pipeline
| Project | Technology | Stage | Capacity | Expected | Where | Operating company |
|---|---|---|---|---|---|---|
| Biomass project | Biomass | Planned (scoping or in planning) | 3 MW | 2027-10-01 | Reken, Nordrhein-Westfalen | Benning Agrar-Energie GmbH |
| Biomass project | Biomass | Planned (scoping or in planning) | 3 MW | 2028-06-30 | Dorsten, Nordrhein-Westfalen | Wulfener Bioenergie GmbH |
| Biomass project | Biomass | Planned (scoping or in planning) | 3 MW | 2028-10-01 | Steinfurt, Nordrhein-Westfalen | Bioenergie Steinfurt GmbH & Co. KG |
| Biomass project | Biomass | Planned (scoping or in planning) | 3 MW | 2028-12-21 | Heiden, Nordrhein-Westfalen | |
| Biomass project | Biomass | Planned (scoping or in planning) | 3 MW | 2030-05-01 | Euskirchen, Nordrhein-Westfalen | |
| Biomass project | Biomass | Planned (scoping or in planning) | 3 MW | 2028-07-01 | Herzebrock-Clarholz, Nordrhein-Westfalen | Brand Bioenergie GmbH Co.KG |
| Biomass project | Biomass | Planned (scoping or in planning) | 3 MW | 2028-04-03 | Raesfeld, Nordrhein-Westfalen | Bioenergie Strothmann KG |
| Biomass project | Biomass | Planned (scoping or in planning) | 3 MW | 2028-04-03 | Raesfeld, Nordrhein-Westfalen | Bioenergie Strothmann KG |
| Biomass project | Biomass | Planned (scoping or in planning) | 3 MW | 2030-05-01 | Euskirchen, Nordrhein-Westfalen | Schornbuscher Biokraft GmbH & Co. KG |
| Biomass project | Biomass | Planned (scoping or in planning) | 2 MW | 2022-12-31 | Bergheim, Nordrhein-Westfalen | LCF Grüne Energie 4 GmbH & Co KG |
| Biomass project | Biomass | Planned (scoping or in planning) | 2 MW | 2022-12-31 | Bergheim, Nordrhein-Westfalen | LCF Grüne Energie 4 GmbH & Co KG |
| Biomass project | Biomass | Planned (scoping or in planning) | 2 MW | 2028-08-01 | Gronau (Westf.), Nordrhein-Westfalen | Biogas Donsel GmbH & Co. KG |
| Biomass project | Biomass | Planned (scoping or in planning) | 2 MW | 2028-08-01 | Gronau (Westf.), Nordrhein-Westfalen | Biogas Donsel GmbH & Co. KG |
| Biomass project | Biomass | Planned (scoping or in planning) | 2 MW | 2028-02-08 | Vreden, Nordrhein-Westfalen | |
| Biomass project | Biomass | Planned (scoping or in planning) | 2 MW | 2028-02-08 | Vreden, Nordrhein-Westfalen | |
| Biomass project | Biomass | Planned (scoping or in planning) | 2 MW | 2028-01-10 | Stadtlohn, Nordrhein-Westfalen | HSI GmbH |
| Biomass project | Biomass | Planned (scoping or in planning) | 2 MW | 2027-06-01 | Stadtlohn, Nordrhein-Westfalen | |
| Biomass project | Biomass | Planned (scoping or in planning) | 2 MW | 2028-10-15 | Ahaus, Nordrhein-Westfalen | |
| Biomass project | Biomass | Planned (scoping or in planning) | 2 MW | 2028-02-01 | Gescher, Nordrhein-Westfalen | Jebing Biogas GmbH & Co. KG |
| Biomass project | Biomass | Planned (scoping or in planning) | 2 MW | 2023-06-01 | Greven, Nordrhein-Westfalen | Biowärme Greven GmbH & Co. KG |
| Biomass project | Biomass | Planned (scoping or in planning) | 2 MW | 2023-06-01 | Greven, Nordrhein-Westfalen | Biowärme Greven GmbH & Co. KG |
| Biomass project | Biomass | Planned (scoping or in planning) | 2 MW | 2022-12-31 | Kranenburg, Nordrhein-Westfalen | LCF Grüne Energie 1 GmbH & Co KG |
| Biomass project | Biomass | Planned (scoping or in planning) | 2 MW | 2022-12-31 | Kranenburg, Nordrhein-Westfalen | LCF Grüne Energie 1 GmbH & Co KG |
| Biomass project | Biomass | Planned (scoping or in planning) | 2 MW | 2028-01-01 | Lemgo, Nordrhein-Westfalen | Stadtwerke Lemgo GmbH |
| Biomass project | Biomass | Planned (scoping or in planning) | 2 MW | 2027-08-31 | Grefrath, Nordrhein-Westfalen | Buschhaus-Mülhausener-Energie GmbH |
Operating companies
| Operating company | Projects | Capacity |
|---|---|---|
| Stadtwerke Düsseldorf AG | 2 | 57 MW |
| GSH Green Steam Hürth GmbH | 2 | 37 MW |
| MVA Bielefeld-Herford GmbH | 1 | 34 MW |
| DHE Dinslakener Holz-Energiezentrum GmbH & Co. KG | 2 | 25 MW |
| EGGER Holzwerkstoffe Brilon GmbH & Co. KG | 2 | 23 MW |
| Kraftwerk Horn GmbH | 1 | 21 MW |
| BMK Biomassekraftwerk Lünen GmbH | 1 | 19 MW |
| Mark-E Aktiengesellschaft | 1 | 18 MW |
| Emschergenossenschaft | 12 | 14 MW |
| Pfleiderer Gütersloh GmbH | 1 | 12 MW |
| Borchers Biomassekraftwerk GmbH | 2 | 11 MW |
| Querdel Energie GmbH | 3 | 10 MW |
| Rheine Bioraffinerie GmbH & Co. KG | 7 | 10 MW |
| Benning Agrar-Energie GmbH | 3 | 9 MW |
| Westag AG | 1 | 9 MW |
| Stromspitzen GmbH & Co. KG | 2 | 9 MW |
| Stadtwerke Detmold GmbH | 3 | 8 MW |
| GBE - Gocher Bioenergie GmbH | 1 | 8 MW |
| Stadtwerke Dinslaken GmbH | 3 | 8 MW |
| LCF Grüne Energie 1 GmbH & Co KG | 4 | 6 MW |
| Biogas Donsel GmbH & Co. KG | 3 | 6 MW |
| Bürger GmbH & Co. KG | 4 | 5 MW |
| medl GmbH | 2 | 5 MW |
| Bioenergie Strothmann KG | 2 | 5 MW |
| Cycleenergy Schameder GmbH | 1 | 5 MW |
Projects of 1 MW and up. Capacity is net nominal capacity (Germany) or the total capacity of the queue entry (Great Britain). A hybrid project counts under each technology it lists. Companies only: private persons are never shown as operators, and no coordinates or street addresses are published. Data as of 2026-10-25, updated monthly.
Germany: Marktstammdatenregister, Bundesnetzagentur, Datenlizenz Deutschland - Namensnennung - Version 2.0 (www.govdata.de/dl-de/by-2-0). Great Britain: Supported by National Energy SO Open Data (NESO Open Data Licence, TEC register and Embedded register).
Questions
Where does this data come from?
Germany: the public Marktstammdatenregister of the Bundesnetzagentur, including units in planning. We load the official files, keep projects of 1 MW and up and record changes between loads.
Does the list show private owners?
No. Operators are shown only when they are companies. Private persons, sole traders and names that could belong to a person are left out, and the data holds no coordinates or street addresses.
How often is it updated?
Monthly. Each load records new projects, changes of stage, capacity or connection date, and projects that left the register.
Cite as: Arcadium Data, "Biomass projects in Nordrhein-Westfalen, Germany: 37 in the pipeline, 73 MW", https://arcadiumdata.io/energy/de/nordrhein-westfalen/biomass/, data as of 2026-10-25.